Bleecker Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct Bleecker Playground.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2022
Projected Completion Date: May 2023
Completion Date: May 2023

Procurement

Start Date: May 2023
Projected Completion Date: May 2024
Completion Date: June 2025

Construction

Start Date: August 2025
Projected Completion Date: August 2026

Understand how we build parks.

Funding

Total Funding: $2,299,000
Funding Source: City Council

Location

Bleecker Playground, Manhattan
Bleecker, Hudson, and West 11th Streets
Community Board: 02

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 07/03/2025