Murray Playground Synthetic Turf Field and Dog Run Reconstruction

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the synthetic turf field, the dog run and northern portions of Murray Playground.

Project Notes

Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.

Project Timeline

Design

Assigned & Start Date: April 2025
Projected Completion Date: April 2026

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • City Council
  • Mayoral

Location

Murray Playground, Queens
45th Avenue 45th Road between 11th and 21st Street
Community Board: 02

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project