Staten Island Forest Restoration

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will remove invasive species and plant new and replacement trees in Staten Island.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2022
Projected Completion Date: March 2023
Completion Date: March 2023

Procurement

Start Date: March 2023
Projected Completion Date: March 2024
Completion Date: June 2025

Construction

Start Date: September 2025
Projected Completion Date: August 2028

Understand how we build parks.

Funding

Total Funding: $1,987,000
Funding Source: Mayoral

Location

Various locations

Project Staff

Contact NYC Parks about this project

Last updated: 07/03/2025