Clove Lakes Parking Lot Green Infrastructure Construction
-
100% complete
-
100% complete
-
0% complete
This project will install green infrastructure within the parking lot at Clove Lakes Park.
Project Notes
Project Update: A date has been set for construction to begin.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2022
Projected Completion Date:
June 2023
Completion Date:
November 2023
Procurement
Start Date: November 2023
Projected Completion Date:
November 2024
Completion
Date:
June 2025
Construction
Start Date: November 2025
Projected Completion Date:
November 2026
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Clove Lakes Park, Staten Island
Martling Avenue and Clove Road
Community Board: 01
Project Staff